The Maharashtra Forest Department has ordered an immediate halt to construction work at Adani Green Energy Limited’s 1,500 MW Tarali Pumped Storage Project in Satara district, citing the absence of prior approval from the National Board for Wildlife (NBWL).

The stop-work direction was issued on November 13, 2026, following an inspection that found project-related activities underway in Patan taluka without the required wildlife clearance. The department has also issued a show-cause notice asking the company to explain why work began before obtaining the approval.
The project has come under scrutiny over two issues: the pending wildlife clearance and a major revision in the estimated project cost, which has implications for the company’s mandatory contribution towards wildlife conservation.
Forest Department Seeks Explanation From Adani Green
The notice issued by the Patan Range Forest Officer directs the company to stop all work until the necessary permissions are obtained. It also asks for a written explanation within three days, along with documents relating to statutory approvals and permissions for tree cutting.
The department has warned that failure to provide a satisfactory explanation and the required documents could invite action under applicable forest and wildlife laws.
The 1,500 MW project is proposed around the Tarali dam reservoir, covering approximately 150.74 hectares of non-forest land across Nivade, Tondoshi, Kalambe and Jalu villages in Patan taluka.
Why the Project Cost Revision Triggered Questions
The project initially had an estimated cost of ₹5,675 crore. However, a notarised affidavit submitted by Adani Green Energy on September 8, 2026, cited a figure of ₹56.75 crore.
The revision attracted attention because the amount payable towards wildlife conservation was linked to the project’s estimated cost. Based on the original figure, the company was required to contribute ₹227 crore, equivalent to 4% of the project cost, towards the Sahyadri Tiger Reserve.
After the revised figure was accepted by the state forest department, the initial deposit was reduced to ₹56.75 lakh, with the remaining contribution to be made after NBWL approval. The total contribution calculated on the revised figure would be approximately ₹2.27 crore.
The issue was raised by Rohan Bhate, honorary wildlife warden of Satara district, who filed complaints with the Prime Minister’s grievance portal and Maharashtra government’s Aaple Sarkar portal. On November 6, the Union Environment Ministry directed the state forest department to investigate the matter on priority.
Adani Green Rejects Allegations
Adani Green Energy has disputed the allegations, stating that ₹56.75 crore represented only the estimated expenditure for site investigation and survey activities, not a revision of the overall project cost.
The company maintains that the complete project cost remains ₹5,675 crore and that the lower figure related to preliminary work such as surveys, geological studies and engineering investigations.
It has also stated that the project is located entirely on private, non-forest land, outside notified protected areas and the buffer zone of the Sahyadri Tiger Reserve. The company says it received environmental clearance in February 2025 and Consent to Establish from the Maharashtra Pollution Control Board in April 2025. Its wildlife clearance proposal is under consideration.
Project Faces Further Scrutiny
The stop-work order has added to the scrutiny surrounding the project, with questions being raised about regulatory approvals, conservation contributions and potential environmental impacts.
On November 17, Maharashtra Forest Minister Ganesh Naik met company representatives to discuss the issue and directed that all applicable rules and financial obligations be followed. The department is examining the company’s clarification before deciding whether to withdraw the stop-work direction.
Summary
Maharashtra has halted work on Adani Green Energy’s 1,500 MW Tarali Pumped Storage Project in Satara over the absence of prior National Board for Wildlife approval. The project also faces scrutiny over a disputed cost figure of ₹56.75 crore against its original ₹5,675 crore estimate. The company says the lower amount covers only survey expenses, while the full project cost remains unchanged.