{"id":1315810,"date":"2026-11-16T08:48:51","date_gmt":"2026-11-16T03:18:51","guid":{"rendered":"https:\/\/trak.in\/stories\/?p=1315810"},"modified":"2026-11-16T08:50:58","modified_gmt":"2026-11-16T03:20:58","slug":"namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033","status":"publish","type":"post","link":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/","title":{"rendered":"Namma Metro&#8217;s Hebbal-Sarjapur Corridor Delayed to April 2033"},"content":{"rendered":"\n<p>Bengaluru\u2019s proposed Hebbal-Sarjapur Metro corridor, part of Namma Metro Phase 3A, is facing another delay, with its expected completion date pushed from 2031 to April 2033. The 37.8-km corridor is still awaiting approval from the Union government, nearly 22 months after Karnataka cleared the project.<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img loading=\"lazy\" decoding=\"async\" width=\"1024\" height=\"545\" src=\"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM-1024x545.png\" alt=\"\" class=\"wp-image-1315816\" srcset=\"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM-1024x545.png 1024w, https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM-300x160.png 300w, https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM-768x408.png 768w, https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM-1536x817.png 1536w, https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM-2048x1089.png 2048w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<p>The proposed Red Line will connect Sarjapur in southeast <a href=\"https:\/\/www.moneycontrol.com\/news\/india\/bengaluru-metro-s-hebbal-sarjapur-corridor-deadline-pushed-to-2033-as-phase-3a-awaits-centre-s-nod-14077229.html\">Bengaluru with Hebbal<\/a> in the north, passing through important commercial and residential areas, including Koramangala and the Central Business District.<\/p>\n\n\n\n<p><strong>Project Cost Revised to \u20b925,999 Crore<\/strong><\/p>\n\n\n\n<p>The Karnataka Cabinet initially approved Phase 3A at an estimated cost of \u20b928,405 crore in December 2024. However, the Union Ministry of Housing and Urban Affairs (MoHUA) raised concerns in June 2025, stating that the proposed cost was higher than its benchmark estimates.<\/p>\n\n\n\n<p>The ministry sought an independent review of the project costs. Following the objections, Bengaluru Metro Rail Corporation Limited (BMRCL) and the state government revised the estimated expenditure to \u20b925,999 crore in 2026.<\/p>\n\n\n\n<p>A revised Detailed Project Report (DPR) was subsequently submitted to the Centre. The cost reduction has not yet resulted in final approval, and the revised project schedule now targets April 2033 for the corridor&#8217;s opening.<\/p>\n\n\n\n<p><strong>Centre&#8217;s Approval Pending for Nearly 22 Months<\/strong><\/p>\n\n\n\n<p>The Karnataka government approved the project in January 2025, but the proposal continues to undergo scrutiny at the central level.<\/p>\n\n\n\n<p>In August 2026, MoHUA informed the Rajya Sabha that the revised DPR was under appraisal. The ministry did not specify when the evaluation would be completed or when the project could receive approval.<\/p>\n\n\n\n<p>Bengaluru Development Minister Krishna Byre Gowda has said the state will seek Prime Minister Narendra Modi&#8217;s intervention to expedite the clearance process.<\/p>\n\n\n\n<p>The state government wants to move ahead with tenders and construction once approval is secured. It is aiming to float tenders and begin work by the end of 2027, subject to the necessary clearances.<\/p>\n\n\n\n<p><strong>Underground Construction Adds to Project Costs<\/strong><\/p>\n\n\n\n<p>One of the major cost factors is the underground section of the proposed corridor.<\/p>\n\n\n\n<p>Of the total 37.8-km alignment, approximately 14.28 km will run underground. The estimated construction cost for this section is around \u20b9695 crore per kilometre.<\/p>\n\n\n\n<p>The state government has argued that Metro construction costs cannot be compared only on a per-kilometre basis. Underground construction, land acquisition, geological conditions and the proportion of elevated tracks can significantly affect project expenditure.<\/p>\n\n\n\n<p><strong>Karnataka Seeks Greater Centre Participation<\/strong><\/p>\n\n\n\n<p>The prolonged approval process has also raised concerns about additional financial pressure on the state government.<\/p>\n\n\n\n<p>Karnataka has highlighted its contribution to earlier Namma Metro phases, stating that it has funded 83.8% of their approved costs, compared with the Centre&#8217;s 16.2%.<\/p>\n\n\n\n<p>The state is seeking faster project clearances and greater central participation in meeting cost escalations arising from delays, design changes and land acquisition.<\/p>\n\n\n\n<p>For Bengaluru commuters, the proposed Sarjapur-Hebbal corridor remains a long-term connectivity project. With central approval still pending, construction cannot proceed as planned, and the revised April 2033 completion target remains dependent on the clearance process.<\/p>\n\n\n\n<p><strong>Summary<\/strong><\/p>\n\n\n\n<p>Bengaluru&#8217;s 37.8-km Hebbal-Sarjapur Metro corridor under Phase 3A has a revised completion target of April 2033, compared with the earlier 2031 deadline. Its estimated cost has been reduced from \u20b928,405 crore to \u20b925,999 crore after central objections. The project is still awaiting Union government approval, delaying the start of construction.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Bengaluru\u2019s proposed Hebbal-Sarjapur Metro corridor, part of Namma Metro Phase 3A, is facing another delay, with its expected completion date pushed from 2031 to April 2033. The 37.8-km corridor is still awaiting approval from the Union government, nearly 22 months after Karnataka cleared the project. The proposed Red Line will connect Sarjapur in southeast Bengaluru [&hellip;]<\/p>\n","protected":false},"author":30,"featured_media":1315816,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"_jetpack_memberships_contains_paid_content":false,"footnotes":""},"categories":[21],"tags":[7102],"class_list":["post-1315810","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-business","tag-namma-metro"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v25.9 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Namma Metro&#039;s Hebbal-Sarjapur Corridor Delayed to April 2033 - Trak.in - Indian Business of Tech, Mobile &amp; Startups<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Namma Metro&#039;s Hebbal-Sarjapur Corridor Delayed to April 2033 - Trak.in - Indian Business of Tech, Mobile &amp; Startups\" \/>\n<meta property=\"og:description\" content=\"Bengaluru\u2019s proposed Hebbal-Sarjapur Metro corridor, part of Namma Metro Phase 3A, is facing another delay, with its expected completion date pushed from 2031 to April 2033. The 37.8-km corridor is still awaiting approval from the Union government, nearly 22 months after Karnataka cleared the project. The proposed Red Line will connect Sarjapur in southeast Bengaluru [&hellip;]\" \/>\n<meta property=\"og:url\" content=\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/\" \/>\n<meta property=\"og:site_name\" content=\"Trak.in - Indian Business of Tech, Mobile &amp; Startups\" \/>\n<meta property=\"article:published_time\" content=\"2026-11-16T03:18:51+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-11-16T03:20:58+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM-1024x545.png\" \/>\n\t<meta property=\"og:image:width\" content=\"1024\" \/>\n\t<meta property=\"og:image:height\" content=\"545\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Mohul Ghosh\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Mohul Ghosh\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/\",\"url\":\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/\",\"name\":\"Namma Metro's Hebbal-Sarjapur Corridor Delayed to April 2033 - Trak.in - Indian Business of Tech, Mobile &amp; Startups\",\"isPartOf\":{\"@id\":\"https:\/\/trak.in\/stories\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM.png\",\"datePublished\":\"2026-11-16T03:18:51+00:00\",\"dateModified\":\"2026-11-16T03:20:58+00:00\",\"author\":{\"@id\":\"https:\/\/trak.in\/stories\/#\/schema\/person\/5092a7d2906e3f3c819643435477c2a7\"},\"breadcrumb\":{\"@id\":\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#primaryimage\",\"url\":\"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM.png\",\"contentUrl\":\"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM.png\",\"width\":2542,\"height\":1352},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/trak.in\/stories\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Namma Metro&#8217;s Hebbal-Sarjapur Corridor Delayed to April 2033\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/trak.in\/stories\/#website\",\"url\":\"https:\/\/trak.in\/stories\/\",\"name\":\"Trak.in - Indian Business of Tech, Mobile &amp; Startups\",\"description\":\"Trak.in is a popular Indian Business, Technology, Mobile &amp; Startup blog featuring trending News, views and analytical take on Technology, Business, Finance, Telecom, Mobile, startups &amp; Social Media Space\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/trak.in\/stories\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Person\",\"@id\":\"https:\/\/trak.in\/stories\/#\/schema\/person\/5092a7d2906e3f3c819643435477c2a7\",\"name\":\"Mohul Ghosh\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/trak.in\/stories\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/66c129d83dd3f325a3b550eb1aa16891173ddfc4686361424206cd9a01311c89?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/66c129d83dd3f325a3b550eb1aa16891173ddfc4686361424206cd9a01311c89?s=96&d=mm&r=g\",\"caption\":\"Mohul Ghosh\"},\"url\":\"https:\/\/trak.in\/stories\/author\/mohul-ghosh\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Namma Metro's Hebbal-Sarjapur Corridor Delayed to April 2033 - Trak.in - Indian Business of Tech, Mobile &amp; Startups","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/","og_locale":"en_US","og_type":"article","og_title":"Namma Metro's Hebbal-Sarjapur Corridor Delayed to April 2033 - Trak.in - Indian Business of Tech, Mobile &amp; Startups","og_description":"Bengaluru\u2019s proposed Hebbal-Sarjapur Metro corridor, part of Namma Metro Phase 3A, is facing another delay, with its expected completion date pushed from 2031 to April 2033. The 37.8-km corridor is still awaiting approval from the Union government, nearly 22 months after Karnataka cleared the project. The proposed Red Line will connect Sarjapur in southeast Bengaluru [&hellip;]","og_url":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/","og_site_name":"Trak.in - Indian Business of Tech, Mobile &amp; Startups","article_published_time":"2026-11-16T03:18:51+00:00","article_modified_time":"2026-11-16T03:20:58+00:00","og_image":[{"width":1024,"height":545,"url":"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM-1024x545.png","type":"image\/png"}],"author":"Mohul Ghosh","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Mohul Ghosh","Est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/","url":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/","name":"Namma Metro's Hebbal-Sarjapur Corridor Delayed to April 2033 - Trak.in - Indian Business of Tech, Mobile &amp; Startups","isPartOf":{"@id":"https:\/\/trak.in\/stories\/#website"},"primaryImageOfPage":{"@id":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#primaryimage"},"image":{"@id":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#primaryimage"},"thumbnailUrl":"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM.png","datePublished":"2026-11-16T03:18:51+00:00","dateModified":"2026-11-16T03:20:58+00:00","author":{"@id":"https:\/\/trak.in\/stories\/#\/schema\/person\/5092a7d2906e3f3c819643435477c2a7"},"breadcrumb":{"@id":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#primaryimage","url":"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM.png","contentUrl":"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM.png","width":2542,"height":1352},{"@type":"BreadcrumbList","@id":"https:\/\/trak.in\/stories\/namma-metros-hebbal-sarjapur-corridor-delayed-to-april-2033\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/trak.in\/stories\/"},{"@type":"ListItem","position":2,"name":"Namma Metro&#8217;s Hebbal-Sarjapur Corridor Delayed to April 2033"}]},{"@type":"WebSite","@id":"https:\/\/trak.in\/stories\/#website","url":"https:\/\/trak.in\/stories\/","name":"Trak.in - Indian Business of Tech, Mobile &amp; Startups","description":"Trak.in is a popular Indian Business, Technology, Mobile &amp; Startup blog featuring trending News, views and analytical take on Technology, Business, Finance, Telecom, Mobile, startups &amp; Social Media Space","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/trak.in\/stories\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Person","@id":"https:\/\/trak.in\/stories\/#\/schema\/person\/5092a7d2906e3f3c819643435477c2a7","name":"Mohul Ghosh","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/trak.in\/stories\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/66c129d83dd3f325a3b550eb1aa16891173ddfc4686361424206cd9a01311c89?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/66c129d83dd3f325a3b550eb1aa16891173ddfc4686361424206cd9a01311c89?s=96&d=mm&r=g","caption":"Mohul Ghosh"},"url":"https:\/\/trak.in\/stories\/author\/mohul-ghosh\/"}]}},"jetpack_featured_media_url":"https:\/\/trak.in\/stories\/wp-content\/uploads\/2026\/11\/Screenshot-2025-05-16-at-10.02.38-AM.png","jetpack_sharing_enabled":true,"_links":{"self":[{"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/posts\/1315810","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/users\/30"}],"replies":[{"embeddable":true,"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/comments?post=1315810"}],"version-history":[{"count":1,"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/posts\/1315810\/revisions"}],"predecessor-version":[{"id":1315817,"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/posts\/1315810\/revisions\/1315817"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/media\/1315816"}],"wp:attachment":[{"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/media?parent=1315810"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/categories?post=1315810"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/trak.in\/stories\/wp-json\/wp\/v2\/tags?post=1315810"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}